This is a Blasting report for an Industrial Wind Farm in Maine

“Blasting is expected to be required for most of the eighteen (18) turbine foundations, the proposed access roads in areas requiring significant cut, the powerline trenches and for above ground transmission line poles. The shallow nature of the soils in the project area suggests that blasting will be required for this project. Soil boring information will be provided in the project’s Geotechnical Engineering Report to be provided in the project’s Final Development Plan.https://www1.maine.gov/DACF/lupc/projects/windpower/redington/redingtonrevised/Documents/Section20_Blasting/Section_08_Blasting_Narrative.pdf